Ormen Lange development project mapOJS Awarded the Entire Langeled Project
June 2006

OJS selection by Allseas this month, to undertake the field joint services on its 2006 section of the Statoil Langeled Trunkline Project, completed the "set" of Langeled contracts for OJS.

In total OJS has been awarded three contracts covering the entire Langeled scope with over 1,100km of field joint infill on the pipeline from Norway to UK, the longest subsea pipeline in the world.

In order to complete this work OJS will procure, ship, provide logistical services and apply over 4,000 tonnes of High Density Polyurethane Foam (HDPF) infill material and 93,000 patented Sea Sleeve/Intrafuse forms. The work shall be performed onboard the LB 200 and Solitaire with the installation program spanning both the 2005 and 2006 pipelay seasons.

OJS Langelend Project Statistics
Contractor Year of Installation Pipeline Dia (ins) Pipeline Length (Km) No. of field joints
Acergy 2005 44 & 42 465 38,200
Allseas 2005 44 & 42 78 6,360
Acergy 2006 42 354 29,000
Allseas 2006 44 238 19,500
Totals 1,135 Km 93,050

During the 465km Acergy pipelay program in 2005, OJS achieved a reliability performance of almost 100% "uptime". Only 8 minutes downtime was recorded in almost 8 months of pipelay operations onboard the LB 200 pipelay vessel.

In addition to the above, the field joint specification for the 2006 part of the trunkline called for an offshore industry first. The energy impact absorption specification for the HDPF was increased to 12.2 Kj compared to the 2005 requirement of 7 Kj. This called for significant re-formulation of the HDPF chemistry by OJS R & D department and extensive pre-qualification testing in Q4 2005.

The LB 200 is currently installing the 2006 pipelay scope and the Solitaire is due to commence mid year. Completion of pipelay is expected in Q4 this year.

OJS Completes the Year with Record Repeat Business Awards
December 2004

In 2004 OJS recorded a remarkable number of clients awarding repeat business contracts worldwide. The clients included Amerada Hess, Allseas, BP, Cairn Energy, Clough, Global, GMC, Horizon, HHI, McDermott, Saipem and Stolt Offshore.

New clients included Heerema, Micoperi, Valentine Maritime and UMAX.

OJS operated in virtually all the offshore regions including Gulf of Mexico, North Sea, Mediterranean, India, Middle East, Caspian Sea, West Africa, Australia, Indonesia, Malaysia, China, Trinidad and the Black Sea,

OJS Wins Largest Field Joint Infill Contract in the History of the Offshore Pipeline Industry (1,000 Km)
November 2004

OJS has been awarded two pipeline field joint infill contracts on the Ormen Lange development project consisting of 900 km of 44"/42" dia. trunkline and 100km of 42"/30" dia. trunkline between Norway and the UK. The combined work provides the largest field joint infill award to a single subcontractor the offshore industry has seen in it extensive history.

The larger scope, the Langeled export system, was awarded by Stolt Offshore AS and the second scope by Solitaire Marine Contractors S.A and Tog Mor Marine Contractors S.A. using the LB 200, Solitaire and Tog Mor vessels respectively. OJS will provide its patented Sea Sleeve and HDPF infill system and its extensive experience of logistics management on large pipelay projects.

The Langeled scope includes the installation of the longest subsea pipeline in the world. The pipeline forms part of the Ormen Lange project and will transport gas from Nyhamna in northern Norway to Easington, England and will provide 20% of the UK gas requirements. Installation is planned from March to September, in both 2005 and 2006.

The Solitaire and Tog Mor work will be performed during the 2005 pipelay season with extensive additional pipelay planned for this field development in 2006.

http://www.offshore-technology.com/projects/ormen/
http://www.offshore-technology.com/projects/snohvit/

OJS Extends Its Presence in the Caspian Sea (400 km)
October 2004

McDermott Caspian Contractors Inc. (MCCI) selected OJS to provide its Sea Sleeve/HDPF infill system for both the Azerbaijan International Operating Co., (AIOC) ACG Phase 2 project and the BP Shah Deniz project in the Caspian Sea. OJS will provide its Sea Sleeve/HDPF infill system on 400 km of pipelines with diameters from 30" to 18". These awards follow OJS completing the ACG Phase 1 of the project earlier in 2004. These two projects will commence early 2005 and continue until year end.

http://www.offshore-technology.com/projects/shah_deniz/

OJS Awarded Four of the Trinidad Pipelay Projects (330 km)
October 2004

Stolt Offshore has selected OJS to provide field joint services on four of its offshore Trinidad pipelay projects. The sequence starts with the BHP Angostura, then NGC Bud, then B.Gas Dolphin Deep and then the B.Gas Cannonball project. The scope totals 252km of the Sleeve/HDPF infill, 67 km of "High Speed" FBE and 14km of Deep Sea Sleeve/Densiflex thermal insulation systems with diameters varying from 36" to 8".

All four projects will be undertaken by the Stolt 801 pipelay vessel from September until March 2005. A fifth project, BP Noel, is still to be awarded and will follow the above projects.

http://www.stoltoffshore.com/

OJS Opens for Business in China
August 2004

OJS has opened a base in China to promote it services and products to the Chinese offshore oil and gas industry. Ashburn International Inc., will represent OJS interests in the region targeting CNOOC and COOEC business opportunities. This is a significant expansion for OJS as the Chinese market is expected to be very active over the foreseeable future.

For future local services please contact:

Tianjin Office
Mr Jun Guo
Email ashburn@public.tpt.tj.cn
Tel 022 235 13318
Fax 022 235 13319
Shenzhen Office
Mr David Yu,
Email yuwei@ashburnsz.com
Tel 86 755 2685 5759
Fax 86 755 2667 1030

OJS Wins Indian MUT Project (500 km)
July 2004

OJS has been awarded a substantial subcontract by Hyundai Heavy Industries (HHI) for field joint infill services on the Mumbai to Uran Trunkline (MUT) pipelay project, offshore India. OJS will provide the patented Sea Sleeve®/HDPF infill system on 500 Km of pipelines with diameters from 30" to 16" O.D. and concrete thicknesses of 30 to 100mm.

OJS will operate onboard all five of HHI fleet of pipelay vessels from December 2004 until May 2005.

OJS Provides Demonstrations of Deepwater Pipeline Field Joint Applications During OTC
May 2004

Representatives from Operators, Design Houses, Installation Contractors, Certifying Authorities and Chemical suppliers worldwide visited the OJS Houston base to witness demonstrations of our Sea Sleeve/HDPF infill, FBE corrosion protection and Deep Sea Sleeve/Densiflex Thermal insulation application systems.

OJS Participates in the World Offshore Pipelay Record
December 2003

During December 2003, OJS was part of a world record in Field Joint Coating Services on board the Allseas pipelay vessel Solitaire. OJS provided field joint services that resulted in 9.2km (5.75m) of pipelay in a single day. This world record was achieved in the Gulf of Mexico, on the Phoenix 18" O.D. (19.05mm W.T.) pipeline project using double joints and Fusion Bonded Epoxy (FBE) anti-corrosion coating. OJS significantly contributed to the reduced cycle time with its 'High Speed' automated field joint blasting, pre-heat and FBE coating equipment and experienced personnel.

Paul Pool, President and Co-Founder of OJS, complimented the team: "This is a remarkable achievement by Allseas and OJS. OJS entered this market sector less than one year ago. Delivering a world record so soon demonstrates the effectiveness of our technology and the commitment of our personnel. We look forward to rapidly expanding this service to other regions in our industry."

In addition to the Phoenix project, OJS was awarded the Gunnison, Marco Polo, and Cameron Highway field joint coating contracts by Allseas. These projects total approximately 650 km (400 miles) of FBE coated pipelines and SCR's installed from either the Solitaire or Lorelay pipelay vessels in the Gulf of Mexico this season.

 

 